Course of construction

The planned completion time is the first half of 2019
Commissioning of Section 3: II quarter 2019
Commissioning of Section 4: II quarter of 2020
Putting into operation 1st and 2nd Sections: the end of 2021

Section 3

Status of works

Reinforcement, concreting of walls and columns of the 11th floor.

  • Building:
    27
    work up to no. 0.000 - 100% carcass - 76% brickwork - 0%
  • Facade:
    5
    window - 0% facade - 5%
  • Accomplishment:
    5
  • Networks:
    0
    internal - 0% external - 0%
Section 4

Status of works

Installation of the formwork for the second part of the slab of the 12th floor. Reinforcement, concreting of walls and columns of the 13th floor.

  • Building:
    29
    work up to no. 0.000 - 100% carcass - 16% brickwork - 0%
  • Facade:
    0
    window - 0% facade - 0%
  • Accomplishment:
    0
  • Networks:
    0
    internal - 0% external - 0%
Section 1

Status of works

Reinforcement grillage building.

  • Building:
    0
    work up to no. 0.000 - 0% carcass - 0% brickwork - 0%
  • Facade:
    0
    window - 0% facade - 0%
  • Accomplishment:
    0
  • Networks:
    0
    internal - 0% external - 0%

Photo from the construction of the 1st, 3rd and 4th sections

15.02.2019
11.02.2019
31.01.2019
24.01.2019
14.01.2019
08.01.2019
26.12.2018
18.12.2018
11.12.2018
04.12.2018
26.11.2018
22.11.2018