Course of construction

Commissioning of Section 3: IV quarter 2020
Commissioning of Section 4: II quarter of 2021
Commissioning of section 1: II quarter 2022

Section 1

Status of works

The installation of the monolithic frame has been completed.

  • Building:
    50
    work up to no. 0.000 - 100% carcass - 100% brickwork - 0% interior decoration - 0%
  • Facade:
    1
    window - 0% facade - 0%
  • Accomplishment:
    5
  • Networks:
    0
    internal - 0% external - 0%
Parking

In section № 3 works on finishing of walls with plaster, installation of the pumping equipment and pipelines take place. Plaster and masonry works are being carried out in section № 4.

Section 2

Status of works

Works on concreting of fragments, columns and the second part of the floor slab at the mark +4.410 are underway.

  • Building:
    26
    work up to no. 0.000 - 100% carcass - 5% brickwork - 0% interior decoration - 0%
  • Facade:
    0
    window - 0% facade - 0%
  • Accomplishment:
    0
  • Networks:
    0
    internal - 0% external - 0%
Section 3

Status of works

Facade finishing works are being completed: fabrication, assembly and installation of the facade system of the 22nd floor, installation of clamps, sash and subsystem under the hinged facade, installation of adjacencies of sandwich panels, triplex fences and waterproofing EPDM-membrane. There is a rise and installation of double-glazed windows. Installation of risers and drainage of atmospheric water from terraces and loggias is carried out. They also install risers and cable lines of the power supply system. Work is underway on the installation of ventilation, heating and smoke removal systems. Finishing works are performed in the lobby: installation of marble. Installation of aquapanels. Plaster works are carried out on stairwells and common areas. Finishing work in the switchboard. On the 5th floor pour screed. On 12-13 floors arrange a heating system. Engineering systems are installed in the apartments. Brickwork of smoke removal mines is carried out.

  • Building:
    77
    work up to no. 0.000 - 100% carcass - 100% brickwork - 99% interior decoration - 0%
  • Facade:
    97
  • Accomplishment:
    5
  • Networks:
    39
    internal - 87% external - 0%
Section 4

Status of works

Works on finishing of a facade pass: installation of arms of a fence, lifting and installation of double-glazed windows, manufacturing, assembly and installation of window designs, the device of a subsystem under a hinged facade. On 7-8 floors the laying of adjacencies to a diaphragm is carried out.

  • Building:
    70
    work up to no. 0.000 - 100% carcass - 100% brickwork - 81% interior decoration - 0%
  • Facade:
    31
  • Accomplishment:
    5
  • Networks:
    0
    internal - 0% external - 0%

Photo from the construction of the 1st, 3rd and 4th sections

15.04.2021
07.04.2021
30.03.2021
23.03.2021
16.03.2021
10.03.2021
03.03.2021
24.02.2021
17.02.2021
11.02.2021
03.02.2021
27.01.2021
22.01.2021
12.01.2021
30.12.2020
23.12.2020
16.12.2020
10.12.2020
03.12.2020
27.11.2020
20.11.2020
11.11.2020
03.11.2020
21.10.2020
15.10.2020
07.10.2020
01.10.2020
23.09.2020
16.09.2020
10.09.2020
03.09.2020
27.08.2020
19.08.2020
14.08.2020
03.08.2020
29.07.2020
23.07.2020
14.07.2020
03.07.2020
25.06.2020
17.06.2020
11.06.2020
03.06.2020
27.05.2020
21.05.2020
12.05.2020
06.05.2020
28.04.2020
21.04.2020
14.04.2020
07.04.2020
31.03.2020
23.03.2020
16.03.2020
05.03.2020
25.02.2020
18.02.2020
03.02.2020
27.01.2020
22.01.2020
15.01.2020
08.01.2020
26.12.2019
12.12.2019
29.11.2019
25.11.2019
14.11.2019
07.10.2019
30.09.2019
20.09.2019
17.09.2019
06.09.2019
02.09.2019
28.08.2019
19.08.2019
12.08.2019
05.08.2019
29.07.2019
22.07.2019
15.07.2019
05.07.2019
01.07.2019
24.06.2019
14.06.2019
10.06.2019
03.06.2019
29.05.2019
17.05.2019
13.05.2019
06.05.2019
02.05.2019
08.04.2019
01.04.2019
26.03.2019
18.03.2019
05.03.2019
25.02.2019
15.02.2019
11.02.2019
31.01.2019
24.01.2019
14.01.2019
08.01.2019
26.12.2018
18.12.2018
11.12.2018
04.12.2018
26.11.2018
22.11.2018
06.11.2018
19.10.2018
03.09.2018
27.08.2018
30.07.2018
02.07.2018
27.06.2018
18.06.2018
12.06.2018
05.06.2018
29.05.2018
22.05.2018
15.05.2018
19.03.2018
21.02.2018
07.02.2018
08.01.2018
28.12.2017
15.11.2017