Section 3: put into operation
Commissioning of Section 4: III quarter of 2022
Commissioning of section 1: I quarter 2023
Status of works
Installation of ventilation units is performed - 98% readiness. Installation of crossbars of facade system is carried out. On 2-3 floors there is a brickwork of walls and partitions.
Section №3 is being plastered, the pumping equipment and pipelines have been installed and painted. Plaster and masonry works are underway in section №4.
Status of works
Reinforcement of vertical elements of the 22nd floor is performed.
Status of works
Facade finishing works are being completed: installation of a hinged ventilated facade, installation of a tire under the glass fence of terraces, installation of a sandwich panel of adjacency and fencing. Work is underway to install a "wet facade". There is a rise and installation of double-glazed windows. Installation of risers and drainage of atmospheric water from terraces and loggias is carried out. Work is underway on the installation of ventilation, heating and smoke removal systems. Brickwork of smoke removal mines is carried out. Entrance doors are installed on floors 14-21.
Status of works
Works on finishing of a facade pass: installation of arms of a fence, lifting and installation of double-glazed windows, manufacturing, assembly and installation of window designs, the device of a subsystem under a hinged facade. On 7-8 floors the laying of adjacencies to a diaphragm is carried out. Plastering works have been started in public places.
Photo from the construction of the 1st, 3rd and 4th sections