Course of construction

Commissioning of Section 3: IV quarter 2019
Commissioning of Section 4: II quarter of 2020
Putting into operation 1st and 2nd Sections: the end of 2021

Section 3

Status of works

Completion of concrete structure of the building. A brickwork is being performed on the 9th, 11th and 12th floors.

  • Building:
    57
    work up to no. 0.000 - 100% carcass - 100% brickwork - 30% interior decoration - 0%
  • Facade:
    5
    window - 0% facade - 5%
  • Accomplishment:
    5
  • Networks:
    0
    internal - 0% external - 0%
Section 4

Status of works

Completion of concrete structure of the building.

  • Building:
    49
    work up to no. 0.000 - 100% carcass - 95% brickwork - 30% interior decoration - 0%
  • Facade:
    0
    window - 0% facade - 0%
  • Accomplishment:
    5
  • Networks:
    0
    internal - 0% external - 0%
Section 1

Status of works

The reinforcement of the first part of the floor slab of the 2 nd floor continues.

  • Networks:
    20
    work up to no. 0.000 - 80% carcass - 0% brickwork - 0% interior decoration - 0%
  • Facade:
    0
    window - 0% facade - 0%
  • Accomplishment:
    0
  • Networks:
    0
    internal - 0% external - 0%
Parking

Work is underway to install a floor slab near the 3rd section.

Photo from the construction of the 1st, 3rd and 4th sections

14.06.2019
10.06.2019
03.06.2019
29.05.2019
17.05.2019
13.05.2019
06.05.2019
02.05.2019
08.04.2019
01.04.2019
26.03.2019
18.03.2019