Course of construction

Commissioning of Section 3: IV quarter 2020
Commissioning of Section 4: II quarter of 2021
Commissioning of section 1: II quarter 2022

Section 1

Status of works

The device of a monolithic framework of columns and diagrams of the 21st floor is carried out.

  • Building:
    47
    work up to no. 0.000 - 100% carcass - 90% brickwork - 0% interior decoration - 0%
  • Facade:
    1
    window - 0% facade - 0%
  • Accomplishment:
    5
  • Networks:
    0
    internal - 0% external - 0%
Parking

In section № 3 the brickwork of partitions of technical premises is executed. The installation of a ramp for entering the parking lot has been completed, as well as the masonry work to connect the parking slab to section № 3. Preparatory work is underway for the installation of fire water tanks. In section № 4 the grille, columns and retaining wall are installed. Work on backfilling and soil compaction is underway. The parking ceiling is 70% ready. The formwork for monolithic plate of overlapping of a part of parking is exposed. Waterproofing of walls is carried out.

Section 2

Status of works

Breakdown of pile heads, reinforcement and preparatory works for pouring grilles are performed. Concreting the foundation preparation.

  • Building:
    2
    work up to no. 0.000 - 8% carcass - 0% brickwork - 0% interior decoration - 0%
  • Facade:
    0
    window - 0% facade - 0%
  • Accomplishment:
    0
  • Networks:
    0
    internal - 0% external - 0%
Section 3

Status of works

Installation of sandwich panels of adjacency and accessories for construction of a fence proceeds. Works on installation of the hinged ventilated and wet facade are carried out. Installation of sash and assembly of the facade system. Installation of risers and drainage of atmospheric water from terraces and loggias is carried out. Water supply and sewerage risers are being laid, combs and water fire extinguishing systems are being installed. They also install risers and cable lines of the power supply system. Finishing works are performed in the lobby: installation of marble. Installation of aquapanels. Finishing work in the switchboard. On 2-3 floors fill in a coupler. On 6-7 floors arrange a heating system. Engineering systems are installed in the apartments. Brickwork of smoke removal mines is carried out.

  • Building:
    75
    work up to no. 0.000 - 100% carcass - 100% brickwork - 99% interior decoration - 0%
  • Facade:
    88
  • Accomplishment:
    5
  • Networks:
    24
    internal - 48% external - 0%
Section 4

Status of works

Installation of a rack and crossbar system of front glazing is carried out. Installation of double-glazed windows. Concrete works are underway, in particular concreting of the parking lot.

  • Building:
    70
    work up to no. 0.000 - 100% carcass - 100% brickwork - 81% interior decoration - 0%
  • Facade:
    9
  • Accomplishment:
    5
  • Networks:
    0
    internal - 0% external - 0%

Photo from the construction of the 1st, 3rd and 4th sections

22.01.2021
12.01.2021
30.12.2020
23.12.2020
16.12.2020
10.12.2020
03.12.2020
27.11.2020
20.11.2020
11.11.2020
03.11.2020
21.10.2020
15.10.2020
07.10.2020
01.10.2020
23.09.2020
16.09.2020
10.09.2020
03.09.2020
27.08.2020
19.08.2020
14.08.2020
03.08.2020
29.07.2020
23.07.2020
14.07.2020
03.07.2020
25.06.2020
17.06.2020
11.06.2020
03.06.2020
27.05.2020
21.05.2020
12.05.2020
06.05.2020
28.04.2020
21.04.2020
14.04.2020
07.04.2020
31.03.2020
23.03.2020
16.03.2020
05.03.2020
25.02.2020
18.02.2020
03.02.2020
27.01.2020
22.01.2020
15.01.2020
08.01.2020
26.12.2019
12.12.2019
29.11.2019
25.11.2019
14.11.2019
07.10.2019
30.09.2019
20.09.2019
17.09.2019
06.09.2019
02.09.2019
28.08.2019
19.08.2019
12.08.2019
05.08.2019
29.07.2019
22.07.2019
15.07.2019
05.07.2019
01.07.2019
24.06.2019
14.06.2019
10.06.2019
03.06.2019
29.05.2019
17.05.2019
13.05.2019
06.05.2019
02.05.2019
08.04.2019
01.04.2019
26.03.2019
18.03.2019
05.03.2019
25.02.2019
15.02.2019
11.02.2019
31.01.2019
24.01.2019
14.01.2019
08.01.2019
26.12.2018
18.12.2018
11.12.2018
04.12.2018
26.11.2018
22.11.2018
06.11.2018
19.10.2018
03.09.2018
27.08.2018
30.07.2018
02.07.2018
27.06.2018
18.06.2018
12.06.2018
05.06.2018
29.05.2018
22.05.2018
15.05.2018
19.03.2018
21.02.2018
07.02.2018
08.01.2018
28.12.2017
15.11.2017

Sales department:

  • city Odessa 65 Frantsuzkyi Avenue
  • info@kandinsky-residence.com.ua
  • Mon - Fri: 10.00 - 20.00
  • Sat - Sun: 10.00 - 18.00
Promotional offers