Course of construction

Commissioning of Section 3: II quarter 2020
Commissioning of Section 4: II quarter of 2020
Putting into operation 1st and 2nd Sections: the end of 2021

Section 3

Status of works

Works on facade decoration are carried out: brickwork of ventilation ducts and partitions.

  • Building:
    73
    work up to no. 0.000 - 100% carcass - 100% brickwork - 93% interior decoration - 0%
  • Facade:
    8
    window - 0% facade - 5%
  • Accomplishment:
    5
  • Networks:
    0
    internal - 0% external - 0%
Section 4

Status of works

The walls of the 10th and 11th floors are laid, the ventilation units are installed.

  • Building:
    61
    work up to no. 0.000 - 100% carcass - 100% brickwork - 45% interior decoration - 0%
  • Facade:
    0
    window - 0% facade - 0%
  • Accomplishment:
    5
  • Networks:
    0
    internal - 0% external - 0%
Section 1

Status of works

The second part of the floor of the 11th floor and the first part of the columns of the 12th floor are being reinforced and concreted.

  • Building:
    36
    work up to no. 0.000 - 100% carcass - 45% brickwork - 0% interior decoration - 0%
  • Facade:
    0
    window - 0% facade - 0%
  • Accomplishment:
    5
  • Networks:
    0
    internal - 0% external - 0%
Parking

Concrete columns, walls and slabs of overlapping are performed.

Photo from the construction of the 1st, 3rd and 4th sections

29.11.2019
25.11.2019
14.11.2019
07.10.2019
30.09.2019
20.09.2019
17.09.2019
06.09.2019
02.09.2019
28.08.2019
19.08.2019
12.08.2019

Sales department:

  • city Odessa 65 Frantsuzkyi Avenue
  • info@kandinsky-residence.com.ua
  • Mon - Fri: 10.00 - 20.00
  • Sat - Sun: 10.00 - 18.00