Course of construction

The planned completion time is the first half of 2019
Commissioning of Section 3: II quarter 2019
Commissioning of Section 4: II quarter of 2020
Putting into operation 1st and 2nd Sections: the end of 2021

Section 3

Status of works

Reinforcement and concreting of walls and columns of the 14th floor.

  • Building:
    27
    work up to no. 0.000 - 100% carcass - 64% brickwork - 0%
  • Facade:
    5
    window - 0% facade - 0%
  • Accomplishment:
    5
  • Networks:
    0
    internal - 0% external - 0%
Section 4

Status of works

Reinforcement of the 2nd part of the overlap of the 2nd floor. Reinforcement and concreting of walls and columns of the 3rd floor. Installation of the formwork of the 1st part of the overlap of the 3rd floor.

  • Building:
    14
    work up to no. 0.000 - 100% carcass - 15% brickwork - 0%
  • Facade:
    0
    window - 0% facade - 0%
  • Accomplishment:
    0
  • Networks:
    0
    internal - 0% external - 0%

Photo from the construction of the 3rd and 4th sections

03.09.2018
27.08.2018
30.07.2018
02.07.2018
27.06.2018
18.06.2018
12.06.2018
05.06.2018
29.05.2018
22.05.2018
15.05.2018
02.05.2018